09年12月的考题分析 {cq; SH
2009年12月F2的考试仍然沿用了50到选择题的方式进行考核。考试时间是2小时,其中40道2分题,10道1分题。总体的考试风格和官网上披露的Pilot paper十分类似,所以在考试前学生必须用Pilot Paper进行模考,把握考试出题的方向并且尽可能留下30分钟左右的时间才进行检查。全球的考试通过率不是太高,但是在高顿国际进行过系统学习的同学,通过率是90%以上。 I zM =?,`
以下是针对2009年12月份考试出现的错误率(大于70%)最高的题目, g9'50<|J
Example 1 l3b$b%0'
A machine is no longer used by a company. It could be sold now for net proceeds of $300. Its only other use is on a short-term contract which is under consideration. The variable running costs of the machine during the period of the contract would be $400. On completion of the contract the machine would have no realisable value and would cost $150 to dismantle and remove. y<8)mw
What is the total relevant cost of using the machine on the contract? (#X/sZQh
A $450 nPR_:_^
B $550 @,pO%,E6
C $700 EX=+TOkAf
D $850 ATk>:^n
官方解释:The correct answer was D. This question tested Sections F2(b) and (c) in the Study Guide, which require candidates to be able to calculate relevant costs for overheads and those for non-current assets. =36vsps=
By not selling the machine now there is an opportunity cost of $300, the variable running cost ($400) are relevant and at the end of the contract the dismantling and removal cost ($150) is also relevant. This gives a total relevant cost of $850.
*N[.']#n
Answer B was chosen by more than 50% of the candidates. This wrong answer could have been obtained in two ways. First as $300 + $400 – $150, the mistake here is to treat the dismantling cost as revenue from the sale of the machine. Second as $400 + $150, the mistake here is to regard the realisable value now as being non-relevant. k "'q
解释:这是一道考核固定资产相关成本的考题。如果现在卖出则获利$300。如果继续使用一段时间,则这段时间需要的投入的成本是$400,并且丢弃时需要用处置成本$150。 那如果选择不卖出那需要花费是成本一共是$400+$150=$550,相对应所放弃的机会成本就是$300。所以这个固定资产的相关成本是$300+$550=$850 g
O gZ
Example 2 %* vYX0W"
A company uses absorption costing with a predetermined hourly fixed overhead absorption rate. Last year, the following situations arose: vA;ml$
(i) Actual overhead expenditure was less than the budgeted expenditure. 91jv=>=DM
(ii) Actual hours worked were less than the budgeted hours used to set the predetermined overhead absorption rate. v9u/<w68!
Which of the following statements is correct? :-ax5,J> q
A Both situations would cause the overheads to be under absorbed ?dC[VYC\^
B Both situations would cause the overheads to be over absorbed k2,n:7
C Situation (i) would cause the overheads to be under absorbed and situation (ii) &